Remote Site Supervision structural works guidebook update

Remote supervision complements physical supervision and does not by itself approve plans or remove professional, permit, inspection, testing or record duties.

Final

BCA's Guidebook for Remote Site Supervision (Structural Works) has Version 2 under a joint BCA/ACES/IES/SCAL circular dated 15 July 2026; BCA describes remote supervision as technology complementing physical supervision by QPs and site supervisors, including pilot use across infrastructure, private projects, fabrication yards and construction sites guidebook version and operating scope

Reference period
15 July 2026 Version 2 circular; annual report 2024/2025; accessed 2 September 2026
Population
Qualified Persons, site supervisors and structural-work project teams in Singapore
Denominator
BCA structural-plan guidance, circular listing and Annual Report 2024/2025
Geography
Singapore

Record details

Metric
version
Source revision
Guidebook for Remote Site Supervision (Structural Works) Version 2

Dates describe this record’s own period and applicability. A verification date does not mean a rule is currently in force.

Sources

  1. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/structural-plan-submission/guidelines-for-st-plan-applications/ Accessed