Permissible timber-scaffold duration

Permissible timber-scaffold duration

Status: provisional

Record details

Value
Three months from 1 January 2027, reduced from nine months
Unit
maximum duration
Value type
observation
Population
Construction worksites using timber scaffolds in Singapore
Denominator
Timber scaffold setup date: pre-2027 setups retain the nine-month duration; new setups from 1 January 2027 are subject to three months
Reference period
From 1 January 2027
Retrieved
2026-09-02
Published
2026-07-02
Geography
sg.geo.country.singapore
Notes
Extensions may be granted case by case for extenuating circumstances. Fire-performance requirements for external scaffold netting were under review and had no published implementation date as at 2 September 2026.