Construction-stage instalments under the developer progressive payment schedule

Housing Developers (Amendment) Rules 2026 state the six construction stages and percentages; commencement is 31 December 2026.

Final

After the initial 20% and before the TOP/CSC stage, six construction-stage instalments total 40%: foundation work including pile caps 10%; reinforced-concrete framework 10%; partition walls 5%; roofing or ceiling 5%; door/window frames, wiring, plastering and plumbing 5%; car park, roads and drains 5%. percentage of contract purchase price

Reference period
Official rule or schedule checked 2026-11-16
Population
Buyers of uncompleted private residential units from licensed housing developers under the prescribed sale-and-purchase form
Denominator
The amended schedule takes effect 31 Dec 2026; each construction instalment is due after notice that its specified stage is complete
Geography
Singapore

Record details

Applies from
2026-12-31
Metric
official grounding

Dates describe this record’s own period and applicability. A verification date does not mean a rule is currently in force.

Sources

  1. https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030 Accessed

Collection as of 2026-11-18 · An expanding collection. Published counts show available knowledge, not complete coverage of Singapore. Machine-readable: JSON · sgobs.housing.progressive-payment-scheme.official-grounding