In Singapore, buyers of uncompleted private homes from licensed developers pay the price in instalments tied to construction milestones: 20% on the option, six stage payments totalling 40%, 25% at TOP or CSC, and a final 15% that partly stays with a stakeholder to cover defects.

# Progressive Payment Scheme for New Private Homes

The progressive payment scheme is how Singapore buyers pay for an uncompleted private home bought directly from a licensed housing developer. Instead of paying the full price on signing, the buyer pays instalments as the developer reports that defined stages of construction are complete, with the final tranche falling due around the Temporary Occupation Permit (TOP) or Certificate of Statutory Completion (CSC). The schedule is written into the prescribed sale and purchase agreement under the Housing Developers Rules, so it is a regulated contract term and not a developer-specific financing offer. This article describes the schedule in the prescribed agreement published in the Housing Developers (Amendment) Rules 2026, which applies from 31 December 2026; where a developer issued an option before that date under the earlier rules, the earlier prescribed agreement continues to apply ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

## The instalment schedule: 20%, 40%, 25% and 15%

Under the prescribed sale and purchase agreement, the purchase price is paid in four blocks. The first is 20% of the price less the booking fee, due on signing the agreement or within eight weeks after the date of the option, so the booking fee and this payment together make up 20% ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

The second block is six construction-stage payments totalling 40%, each due within 14 days after the buyer receives the developer's notice that the stage is complete: foundation work including pile caps (10%), reinforced concrete framework (10%), partition walls (5%), roofing or ceiling (5%), door and window frames with electrical wiring, internal plastering and plumbing (5%), and the car park, roads and drains serving the project (5%). The developer may give the stage notices in any order ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

The third block is 25% of the price, due within 14 days after the buyer receives the TOP or CSC for the unit and notice that the building, roads, drainage and sewerage works are complete and that water, electricity and any gas supplies are connected. The remaining 15% follows the arrangement described below ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)). The four blocks add up to 100% of the purchase price. The percentages apply to the contract price, so the cash sum for each stage scales with the price of the unit.

## The last 15% and the stakeholder holdback

The final 15% of the price is split so that part of it is held back while defects can still be claimed. In the prescribed agreement, a stakeholder, the Singapore Academy of Law (SAL), holds 5% of the price until the Final Payment Date, and the buyer may serve a written notice of deductions for unit or common-property defects at least seven working days before the relevant defects liability period ends. The SAL then pays the developer the stakeholder money less any deductions duly notified and not disputed, and retains any disputed amount until the dispute is settled ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within); [Singapore Academy of Law, accessed 16 November 2026](https://sal.org.sg/trust-services/)).

How the final 15% is divided depends on the order of three events: the CSC, the Completion Date (when the sale is completed) and the Final Payment Date. Two examples from the agreement show the pattern. Where the CSC is issued before both the Completion Date and the Final Payment Date, the buyer pays 13% within 14 days after receiving the CSC, of which 8% goes to the developer and 5% to the SAL for release on the Final Payment Date less authorised deductions, and the last 2% on the Completion Date. Where the Final Payment Date falls before the Completion Date and the CSC comes later, the buyer pays 5% within 14 days after notice of the Final Payment Date, then 10% on the Completion Date, of which 2% goes to the developer and 8% to the SAL for release within seven working days after the SAL receives the CSC ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)). Other orderings produce other splits, so a buyer should read the payment schedule in the signed agreement and not assume either example applies.

## Notices, project account and late-payment consequences

Each stage notice must be accompanied by a copy of the certificate of the Housing Project Qualified Person confirming that the specified works are complete, and that certificate is conclusive of completion, which the buyer must accept without further objection or enquiry. Instalments due to the developer under the first three blocks are paid to the project account named in the agreement by crossed cheque, cashier's order or electronic transfer ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

Time is of the essence for instalments. A buyer who fails to pay an instalment on time owes interest at 2% per annum above the Base Rate, defined in the agreement as the three-month compounded Singapore Overnight Rate Average published by the Monetary Authority of Singapore on 1 March or 1 September, depending on the period ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)). The developer has reciprocal duties. If the developer fails to deliver vacant possession by the agreed deadline, the agreement provides for liquidated damages, which the buyer may deduct from instalments due to the developer ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

## Key collection, defects periods and 2026 changes

URA describes the last stages in practical terms: once the TOP is issued and the buyer has paid the progress payment due upon TOP, the developer explains the key-collection procedure, and defects can then be reported for rectification during the defects liability period ([URA, Buying Property, updated 6 November 2026](https://www.ura.gov.sg/guidelines/property-and-business-owners/property/buying-property/)).

From 31 December 2026, the Defects Liability Period (DLP) and the buyer's liability for maintenance charges start together on the earlier of the 35th day after the buyer receives the notice of TOP payment and the date vacant possession is delivered. The DLP for an individual unit stays at 12 months; the DLP for common property is extended to 12 months from the start date or six months after the first annual general meeting of the management corporation, whichever is later ([URA circular, 30 October 2026](https://www.ura.gov.sg/guidelines/circulars/coh26-03/)). Separately, if a buyer objects in writing to a substantive change to the plans and the developer annuls the agreement on at least 21 days' notice, the developer must refund all amounts paid without interest, pay back the ad valorem stamp duty paid (subject to the agreement's conditions), and reimburse loan interest, any loan cancellation charge and legal fees up to 5% of the purchase price ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, clauses 14.4-14.7, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

## How to read the schedule

The progressive payment scheme sets when the price is paid, not how it is financed. Whether a buyer funds an instalment from cash, CPF Ordinary Account savings or a bank loan is a separate matter governed by CPF and lending rules ([cpf housing usage](/en/knowledge/article/sgkb.cpf-social-security.cpf-housing-usage), [cooling measures and absd](/en/knowledge/article/sgkb.housing.cooling-measures-and-absd)). The stage dates are triggered by notices, not calendar dates, so a buyer cannot read a fixed payment calendar from the contract. Stamp duties are paid separately within the periods IRAS sets. For the earlier option stage, including the 5%-10% booking fee and the three-week option period, see [option to purchase private homes](/en/knowledge/article/sgkb.housing.option-to-purchase-private-homes). This schedule applies to developer sales of uncompleted units; completed resale homes are sold on negotiated terms ([private property market](/en/knowledge/article/sgkb.housing.private-property-market)). Because options issued before 31 December 2026 stay on the earlier forms, the date the OTP was issued determines which version of the schedule governs a given purchase ([Singapore Statutes Online, Housing Developers (Amendment) Rules 2026, accessed 9 November 2026](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within)).

## Sources

- [Singapore Statutes Online — Housing Developers (Amendment) Rules 2026 (prescribed OTP and sale and purchase agreement)](https://sso.agc.gov.sg/SL-Supp/S813-2026/Published/20261030?DocDate=20261030&ViewType=Within) — Accessed 2026-11-09
- [URA — Strengthening the Housing Developers Rules (circular, 30 October 2026)](https://www.ura.gov.sg/guidelines/circulars/coh26-03/) — Accessed 2026-11-09
- [URA — Buying Property (updated 6 November 2026)](https://www.ura.gov.sg/guidelines/property-and-business-owners/property/buying-property/) — Accessed 2026-11-09
- [Singapore Statutes Online — Housing Developers Rules](https://sso.agc.gov.sg/SL/HDCLA1965-R1?DocDate=20261030) — Accessed 2026-11-09

## Explore connections

- Articles: [Buying a Condominium in Singapore: Step by Step](https://ik.sg/en/knowledge/article/sgkb.housing.condo-buying-process-singapore)
- Articles: [Executive Condominium Eligibility and Minimum Occupation Period](https://ik.sg/en/knowledge/article/sgkb.housing.executive-condominium-eligibility-and-mop)
- Articles: [Foreigners Buying Condominiums in Singapore](https://ik.sg/en/knowledge/article/sgkb.housing.foreigners-buying-condo-singapore)
- Articles: [Home-Loan Packages and Refinancing](https://ik.sg/en/knowledge/article/sgkb.housing.home-loan-packages-and-refinancing)
- Articles: [New Launch vs Resale Condominiums in Singapore](https://ik.sg/en/knowledge/article/sgkb.housing.new-launch-vs-resale-condo)
- Articles: [Option to Purchase for Private Homes](https://ik.sg/en/knowledge/article/sgkb.housing.option-to-purchase-private-homes)
- Articles: [Private Residential Property Market](https://ik.sg/en/knowledge/article/sgkb.housing.private-property-market)
- Articles: [Property Cooling Measures and Stamp Duties](https://ik.sg/en/knowledge/article/sgkb.housing.cooling-measures-and-absd)
- Articles: [Upfront Costs of Buying a Private Condominium](https://ik.sg/en/knowledge/article/sgkb.housing.private-condo-purchase-costs)
- Articles: [Using CPF for Housing](https://ik.sg/en/knowledge/article/sgkb.cpf-social-security.cpf-housing-usage)
- Articles: [Using CPF to Buy a Private Condominium](https://ik.sg/en/knowledge/article/sgkb.housing.cpf-for-private-condo-purchase)
- Topics: [Housing](https://ik.sg/en/knowledge/topic/sgtopic.housing)
- Topics: [Progressive Payment Scheme for new private homes](https://ik.sg/en/knowledge/topic/sgtopic.housing.progressive-payment-scheme)
- People & organisations: [Building and Construction Authority](https://ik.sg/en/knowledge/entity/sg.agency.bca)
- People & organisations: [Monetary Authority of Singapore](https://ik.sg/en/knowledge/entity/sg.agency.mas)
- People & organisations: [Singapore Academy of Law](https://ik.sg/en/knowledge/entity/sg.organisation.singapore-academy-of-law)
- Life journeys: [Buying a home in Singapore](https://ik.sg/en/knowledge/journey/sgjourney.home-purchase)

Dates describe this record’s own period and applicability. A verification date does not mean a rule is currently in force. An expanding collection. Published counts show available knowledge, not complete coverage of Singapore.