# Inter-Agency Coordinating Committee Resolution Platform

BCA's IACC Resolution platform helps project teams resolve conflicting regulatory requirements across agencies; a FormSG lodgement portal launched on 1 September 2026 to replace email submissions.

# Inter-Agency Coordinating Committee Resolution Platform

The **Inter-Agency Coordinating Committee (IACC) Resolution platform** is a Singapore construction-project channel for resolving issues caused by conflicting regulatory requirements across two or more agencies. BCA's circular dated **1 September 2026** says the platform has handled cases lodged by industry practitioners since 2019 and that IACC holds regular monthly resolution meetings. Its purpose is to help project teams surface cross-agency regulatory conflicts early, so that issues can be clarified before they become clearance or construction delays ([BCA, 1 September 2026](https://isomer-user-content.by.gov.sg/338/ea99df85-8092-45c4-b9a0-f8606f58481f/FINAL%20Industry%20Circular.pdf)).

## FormSG lodgement change

The new **FormSG** portal at [go.gov.sg/iacc-lodgement](https://go.gov.sg/iacc-lodgement) was scheduled to go live on **1 September 2026**. It replaces the previous email-based submission process for new IACC case lodgements. BCA says FormSG is designed to guide industry users to provide more complete and higher-quality information at first lodgement, and to enable concurrent dissemination of a case to relevant agencies rather than relying only on sequential workflows. New cases submitted by email are directed to the FormSG portal under the revised process ([BCA, 1 September 2026](https://isomer-user-content.by.gov.sg/338/ea99df85-8092-45c4-b9a0-f8606f58481f/FINAL%20Industry%20Circular.pdf)).

## What the platform resolves

The platform is for project issues arising from conflicting or competing regulatory requirements between agencies. Under the earlier process, the IACC Secretariat could seek clarification from a project team before disseminating a case to relevant agencies. The revised workflow aims to identify information gaps earlier and allow agencies to consider a case concurrently. This is a coordination and resolution route; it does not itself grant planning permission, building approval, a regulatory exemption or a decision that overrides an individual agency's statutory requirements ([BCA, 1 September 2026](https://isomer-user-content.by.gov.sg/338/ea99df85-8092-45c4-b9a0-f8606f58481f/FINAL%20Industry%20Circular.pdf)).

## Who participates and what to prepare

BCA describes IACC as a tripartite coordinating committee formed in July 2011. It brings together regulators, public-sector developers and built-environment trade associations, and is chaired by BCA's Deputy Chief Executive Officer (Building Control). Standing regulatory members include BCA, LTA, NEA, NParks, PUB, SCDF and URA; EMA and IMDA are also represented. JTC, HDB and Town Councils represent public-sector developers, while ACES, IES, REDAS, SCAL and SIA represent industry. Beyond individual project conflicts, IACC can act as a sounding board on new rules and help identify systemic clashes or cross-agency process improvements. For a project-level case, BCA asks applicants to provide a clear account of the issue, supporting drawings or other documents and relevant agency discussions, the outcome sought, and any proposed alternative solution after considering agencies' responses. The resolution process starts once the case is sufficiently clear for agencies to assess ([BCA, IACC page](https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/building-plan-submission/inter-agency-coordinating-committee-iacc/)).

## Reported resolution performance and interpretation

BCA's circular reports that **more than 90%** of cases lodged from **2021 onwards** were effectively resolved within **three months**, based on recent IACC records. The percentage describes the cases and period covered by that statement; it is not a guarantee that a new case will be resolved within three months and does not establish that every regulatory conflict is eligible or technically solvable through IACC. Project practitioners are encouraged to surface issues as early as necessary to minimise potential impasses in project clearance and construction ([BCA, 1 September 2026](https://isomer-user-content.by.gov.sg/338/ea99df85-8092-45c4-b9a0-f8606f58481f/FINAL%20Industry%20Circular.pdf)).

## Sources

- [BCA — Inter-Agency Coordinating Committee (IACC)](https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/building-plan-submission/inter-agency-coordinating-committee-iacc/) — Accessed 2026-11-08
- [BCA — IACC Resolution Platform: Launch of FormSG](https://isomer-user-content.by.gov.sg/338/ea99df85-8092-45c4-b9a0-f8606f58481f/FINAL%20Industry%20Circular.pdf) — Accessed 2026-09-01
- [BCA — IACC FormSG lodgement portal](https://go.gov.sg/iacc-lodgement) — Accessed 2026-09-01

## Explore connections

- Articles: [Post-Installed Anchor Safety Guidance](https://ik.sg/en/knowledge/article/sgkb.geography-urban-planning.post-installed-anchor-safety)
- Articles: [URA and the Master Plan](https://ik.sg/en/knowledge/article/sgkb.geography-urban-planning.ura-and-master-plan)
- Topics: [Geography and urban planning](https://ik.sg/en/knowledge/topic/sgtopic.geography)
- Topics: [Inter-Agency Coordinating Committee Resolution Platform](https://ik.sg/en/knowledge/topic/sgtopic.geography-urban-planning.iacc-resolution-platform)
- People & organisations: [Building and Construction Authority](https://ik.sg/en/knowledge/entity/sg.agency.bca)
- People & organisations: [National Parks Board](https://ik.sg/en/knowledge/entity/sg.agency.nparks)

Dates describe this record’s own period and applicability. A verification date does not mean a rule is currently in force. An expanding collection. Published counts show available knowledge, not complete coverage of Singapore.